We have wrapped up the parking lot paving and striping. The exterior painting on the façade will be complete by the end of the week. Interior the multipurpose building is complete and ready for students to start school next week!
Read More
The gym flooring is almost completely installed and will be ready for final inspection next week. The Multipurpose building is framed and the mechanical, electrical, and plumbing are roughed in. The finishes are gearing up to start with this building scheduled to be complete in early August.  The parking lot curb is being installed, the...
Read More
The roof is officially dried in and the interior of the gym is framed! We are currently roughing in mechanical, plumbing, and electrical. The inside of the gym is beginning to resemble the finished product. We’ll be ready to drywall soon! Additionally, construction of the MP Building will begin next month. Material ordering and trade...
Read More
Raise the roof! The roof and deck are installed and we are currently stocking the roofing with the roofing membrane to start drying the building in. Inside the building we are framing the restrooms and have started running wire inside the stage. Pretty soon the stage will be used for student performances!
Read More
Today we set the joists for the roof! Check out the video below.
Read More
The new gym walls are almost complete! We are scheduled to finish the masonry walls by the end of this week. From there, we are preparing to fly the roofing steel joists on Monday the 18th (stay tuned for a video!). On site we are running the storm sewer from the parking lot to the...
Read More
The building shell is almost complete! We’ve reached the top of the building on 2 sides and are close to wrapping up the others. As soon as the masonry walls are complete we will begin to fly the roofs steel beams to complete the structural shell. On site the fire line has been completely installed...
Read More
It’s starting to look more like a gym out here! The masonry walls are currently going up. As they go up, our electrician is on hand to install all conduit and fixture boxes. Within the next few weeks the shell of your new gym will be complete! Additionally, we’ve been installing the underground fire line...
Read More
Over the past couple of weeks we’ve had a lot of heavy equipment moving dirt on site. The new retention basin was graded, drywell dug out, and the most exciting, THE NEW GYM PAD IS READY! GO TIGERS! In the next few weeks we’ll be prepping the building to go vertical (aka building the walls)...
Read More
CHASSE Building Team has broken ground onsite at the Biltmore Preparatory Academy. We’re excited for construction to begin! In the month of November we will be working on underground utilities and footings. More updates to follow!
Read More