Aiming to pave!

The gym flooring is almost completely installed and will be ready for final inspection next week. The Multipurpose building is framed and the mechanical, electrical, and plumbing are roughed in. The finishes are gearing up to start with this building scheduled to be complete in early August. 

The parking lot curb is being installed, the grading is progressing, and we are aiming to pave in mid -July!