News & Updates

24
Jul

Almost done!

We have wrapped up the parking lot paving and striping. The exterior painting on the façade will be complete by the end of the week. Interior the multipurpose building is complete and ready for students to start school next week!
Read More
20
Jun

Aiming to pave!

The gym flooring is almost completely installed and will be ready for final inspection next week. The Multipurpose building is framed and the mechanical, electrical, and plumbing are roughed in. The finishes are gearing up to start with this building scheduled to be complete in early August.  The parking lot curb is being installed, the grading is progressing, and we are aiming to pave in mid -July!
Read More
26
Mar

Almost time for drywall!

The roof is officially dried in and the interior of the gym is framed! We are currently roughing in mechanical, plumbing, and electrical. The inside of the gym is beginning to resemble the finished product. We’ll be ready to drywall soon! Additionally, construction of the MP Building will begin next month. Material ordering and trade scheduling is well underway.
Read More
11
Mar

Raise the roof!

Raise the roof! The roof and deck are installed and we are currently stocking the roofing with the roofing membrane to start drying the building in. Inside the building we are framing the restrooms and have started running wire inside the stage. Pretty soon the stage will be used for student performances!
Read More
19
Feb

Video: Setting joists!

Today we set the joists for the roof! Check out the video below.
Read More
10
Feb

Walls are almost complete!

The new gym walls are almost complete! We are scheduled to finish the masonry walls by the end of this week. From there, we are preparing to fly the roofing steel joists on Monday the 18th (stay tuned for a video!). On site we are running the storm sewer from the parking lot to the retention behind the gym and are anticipating being done with that this week as well.
Read More
28
Jan

Going vertical continued…

The building shell is almost complete! We’ve reached the top of the building on 2 sides and are close to wrapping up the others. As soon as the masonry walls are complete we will begin to fly the roofs steel beams to complete the structural shell. On site the fire line has been completely installed and we’re now working on the storm sewer.
Read More
12
Jan

Going vertical!

It’s starting to look more like a gym out here! The masonry walls are currently going up. As they go up, our electrician is on hand to install all conduit and fixture boxes. Within the next few weeks the shell of your new gym will be complete! Additionally, we’ve been installing the underground fire line in the parking lot.
Read More
27
Nov

Prepping for walls!

Over the past couple of weeks we’ve had a lot of heavy equipment moving dirt on site. The new retention basin was graded, drywell dug out, and the most exciting, THE NEW GYM PAD IS READY! GO TIGERS! In the next few weeks we’ll be prepping the building to go vertical (aka building the walls) by pouring the footings. Footings are concrete reinforced with rebar that outline the entire building. This is the basis for a strong building foundation. The...
Read More
1 2